INTEGRATED ENERGY ECOSYSTEM:
ILLUSTRATIVE EXECUTION SCOPE · REPRESENTATIVE PROJECT FRAMEWORK · AE-03

PCC & MCC Panel Fabrication & Installation

Representative framework for engineering, fabricating, inspecting, and commissioning compartmentalized IP54 Power Control Centres (PCC) and Motor Control Centres (MCC) for industrial manufacturing floors.

Framework Disclosure: AE-03 is published as an Illustrative Execution Scope / Representative Project Framework detailing AAROHAN ELECTRICALS' standardized execution sequence, applicable IS/IEC standards, and handover deliverables.
Division E2 · LT Panels

Technical Framework Parameters

Construction StandardIS 8623 / IEC 61439, 14/16 SWG CRCA, IP54
Incomer / Fault Level1250A Draw-Out ACB, 50 kA for 1 sec
Motor FeedersDOL, Star-Delta, Soft-Starter & VFD Bays
Metering & SafetyDigital MFM (RS-485), Shrouded Busbars, Earth Bar
EXECUTION & TESTING DELIVERABLES

Standardized Site Execution Sequence

  • GA & SLD drawing approval with feeder schedules, busbar cross-section & cable alley sizing
  • 7-tank powder-coated enclosure fabrication with neoprene gaskets & vermin-proof louvers
  • Factory Acceptance Test (FAT): 2.5 kV HV dielectric test, functional trip & interlock checks
  • Base channel grouting, panel erection, cable dressing & IS 15652 insulating rubber mat placement
  • As-built panel schematic & breaker setting schedule handover